| PAYMENT SCHEDULE |
| On Booking |
10% of the BSP |
| Within 60 days from the Booking |
10% of BSP |
| Within 120 days from the booking or issue of Builder Buyer Agreement whichever is later |
10% of BSP |
| On excavation |
5% of BSP |
| On Casting of 2nd Basement Floor Slab |
7.5 % + 25% of EDC and IDC+ PLC (if applicable ) |
| On Casting of 1st Basement Floor Slab |
5 %+ 25% of EDC and IDC + PLC (if applicable ) |
| On Casting of Ground Floor Slab |
7.5 %+ 25% of EDC and IDC + PLC (if applicable ) |
| On Casting of 3rd Floor Slab |
5 %+ 25% of EDC and IDC + PLC (if applicable ) |
| On Casting of 6th Floor Slab |
5% of the BSP + 25% of Car Parking |
| On Casting of 9th Floor Slab |
7.5 %+ 25% of Car Parking |
| On Casting of 12th Floor Slab |
7.5 %+ 25% of Car Parking |
| On Installation of Plumbing |
7.5 %+ 25% of Car Parking |
| On Installation of Electrical |
7.5% of BSP |
| On Notice of Possession |
5% + other charges |